New Gym

 

October 1 2017

We’ve got all the painting done and the carpet is down on the basketball court. We still have to put tile down on the rest of the floors and then we will be ready for the finishing touches. We are so excited about what God is going to allow us to do with this new building. To HIM be all the glory!

Read more...

February 7 2015

Getting some walls up

Read more...

June 17 2014

Working Inside- Electrical

Read more...

April 21 2014

Weekly Progress Report
 
We had a building committee meeting last night at 7pm- all men or interested people who want to work on the new gym are always invited every Monday evening at 7pm. Work is progressing on getting the septic system and electrical materials ordered.

Read more...

April 15 2014

Building is up -what now?
 
The shell is complete! Now the fun (and slow) part begins! We will be asking for volunteers to participate on some Saturday workdays very soon, just not yet. Right now, we are trying to line up septic system work and obtain the materials for the electrical rough-in. We will announce in church when your help is needed, and there will be plenty of work to go around! Thank you so much for your support of this project, it is for the Glory of God!

Read more...

April 1 2014

New Gym is dried-in!

Read more...

March 15 2014

 width=
Coming right along!

Read more...

February 20 2014

Concrete pad is poured!

Read more...

February 9 2014

We have gravel!

Read more...

August 24 2013

Here  comes the dirt!

Read more...

March 1 2013

Site of the new Building!

Read more...